63230-507-201A1 Power Meter 750
03/2007 Section 4—Metering
© 2007 Schneider Electric All Rights Reserved
17
Demand Power Calculation Methods Demand power is the energy accumulated during a specified period divided
by the length of that period. How the power meter performs this calculation
depends on the method you select. To be compatible with electric utility
billing practices, the power meter provides the following types of demand
power calculations:
Block Interval Demand
Synchronized Demand
Thermal Demand
The default demand calculation is set to sliding block with a 15 minute
interval. (You can set up the other demand power calculation methods only
through communications.)
Block Interval Demand In the block interval demand method, you select a “block” of time that the
power meter uses for the demand calculation. You choose how the power
meter handles that block of time (interval). Three different modes are
possible:
Sliding Block. In the sliding block interval, you select an interval from 1
to 60 minutes (in 1-minute increments). The power meter displays the
demand value for the last completed interval.
Fixed Block. In the fixed block interval, you select an interval from 1 to
60 minutes (in 1-minute increments). The power meter calculates and
updates the demand at the end of each interval.
Rolling Block. In the rolling block interval, you select an interval and a
subinterval. The subinterval must divide evenly into the interval. For
example, you might set three 5-minute subintervals for a 15-minute
interval. Demand is updated at each subinterval. The power meter
displays the demand value for the last completed interval.
Figure 4– 1 illustrates the three ways to calculate demand power using the
block method. For illustration purposes, the interval is set to 15 minutes.
Demand Reactive Power, 3Ø Total
Last Complete Interval
Peak
0 to 3276.70 MVAR
0 to 3276.70 MVAR
Demand Apparent Power, 3Ø Total
Last Complete Interval
Peak
0 to 3276.70 MVA
0 to 3276.70 MVA
Table 4– 2: Demand Readings (continued)